Major Highway 1 work gets underway in Fraser Valley

The route serves a growing region and is used by more than 80,000 drivers each day.

More than $65 billion in goods move along the corridor annually.

Key Takeaways:

  • $2.34 billion of highway improvement work is underway from the Fraser Valley to the Sumas Prairie.
  • It is Phase 3A of the Province’s Fraser Valley Highway 1 Corridor Improvement Program, a multi-phase program to improve goods movement and travel along Highway 1 in the Fraser Valley through the Sumas Prairie to Chilliwack.
  • Two more tenders are on track for release, including a new interchange at 232nd Street and highway widening for HOV lanes, along with a replacement to the existing CP Rail overhead.   

The Whole Story:

The next phase of multi-billion dollar Highway 1 expansion project has begun. 

The project will expand Highway 1 through the Fraser Valley to the Sumas Prairie.

Officials say the work will relieve traffic congestion and accommodate more sustainable transportation options in the region.

Accelerated advance work along the Highway 1 median east of 264th Street has begun, with work delivered by local companies including Kwantlen First Nation. People travelling Highway 1 will see crews in the median undertaking utility relocation, median soil removal, tree clearing and preloading of soil. This work will prepare the area between 264th Street and Mt. Lehman Road for the addition of high occupancy vehicle (HOV)/electric vehicle lanes and other multi-modal upgrades.

“The Fraser Valley is growing fast and we are building infrastructure that people need,” said Rob Fleming, minister of transportation and infrastructure. “People need to be able to get to work and back home without facing gridlock. We’re taking action to relieve congestion for drivers, to make goods movement more efficient and to accommodate more sustainable transportation options.”

The widening of Highway 1 between 264th Street and Mt. Lehman Road has an approved budget of $2.34 billion. This is Phase 3A of the Province’s Fraser Valley Highway 1 Corridor Improvement Program, a multi-phase program to improve goods movement and travel along Highway 1 in the Fraser Valley through the Sumas Prairie to Chilliwack.

The centrepiece of Phase 3A will be a new 264th Street Interchange, reconfigured to better serve road users. Officials say the 264th Street area is highly travelled during morning and afternoon hours, including a high volume of commercial vehicles heading to and from the border crossing. Along with more efficient goods movement, the new interchange will include improvements for active transportation, truck parking and public transit. The new interchange is in procurement, with construction expected to begin in 2024.

The 264th Street Interchange and associated highway widening is one of the three major construction contracts that make up Phase 3A. The other contracts will be upgrades to the Mt. Lehman Interchange and 3.7 kilometres of highway widening, and replacement of the Bradner Road overpass with 3.9 kilometres of highway widening. These contracts will go to tender in 2024. Completion of Phase 3A is expected in 2029.

Work is underway on Phase 2 between 216th and 264th streets, with a new Glover Road overpass currently under construction and completion expected in summer 2024. 

Two more tenders are on track for release, including a new interchange at 232nd Street and highway widening for HOV lanes, along with a replacement to the existing CP Rail overhead.   

Further east along Highway 1 between Mt. Lehman Road and Highway 11, advanced site-preparation work is planned for early 2024 ahead of construction on that phase of the program.

The scope of the program has expanded and a fourth phase extends through the Sumas Prairie into Chilliwack. Officials explained that this future phase of the Fraser Valley Highway 1 Improvement Program through the Sumas Prairie will address the need for improvements to infrastructure to make it more resilient to changing climate.

The Ministry of Transportation and Infrastructure has committed $30 million to an integrated planning study, which is happening in parallel with flood-mitigation strategy planning work. This study will identify potential future improvements along the Trans-Canada Highway corridor between the Sumas Prairie and Chilliwack.

Share

Get smarter on the 🇨🇦 construction industry in just 5 minutes

Sign up for the free weekly newsletter for news, trends and insights in the Canadian construction industry.

Construction job board

Discover senior-level construction jobs at leading companies in Canada.

Find a jobPost a job

Topics

Newsletter

Get the 5-minute, weekly newsletter about the Canadian construction industry.

© SiteNews 2024. All rights reserved. SiteNews is an independently-operated news website. Views expressed are that of the editor's and are based on publicly available information unless otherwise noted through sponsored content.