B.C. natural gas pipeline has been substantially started

The environmental assessment certificate will now be in effect for the life of the project.

Key Takeaways:

  • The Environmental Assessment Office (EAO) has ruled that the Prince Rupert Gas Transmission pipeline project has been substantially started, allowing its 2014 environmental assessment certificate to remain valid indefinitely, provided it is not suspended or cancelled.
  • The project, now owned by the Nisga’a Nation and Western LNG (acquired from TC Energy in March 2024), is proposed to supply the Ksi Lisims LNG facility and is undergoing assessment for two major route amendments—one to end at Pearse Island and another to reroute part of the eastern section for efficiency.
  • The EAO will continue compliance monitoring throughout construction and operation. The pipeline is designed to transport 2 billion cubic feet of natural gas per day, with future expansion potential up to 3.6 billion cubic feet per day.

The Whole Story:

The chief executive assessment officer of the Environmental Assessment Office (EAO) has determined that the Prince Rupert Gas Transmission (PRGT) natural gas pipeline project has been substantially started.

With this decision, the certificate remains in effect for the life of the project, unless it is cancelled or suspended pursuant to the Environmental Assessment Act. The environmental assessment certificate approving the PRGT project was issued in 2014, following the EAO’s environmental assessment. The certificate required the project to have been substantially started by Nov. 25, 2024, for it to remain valid.

The EAO undertook a detailed assessment process that started at the end of November 2024, examining all evidence relevant to the matter of whether or not the project is substantially started. First Nations potentially impacted by the project had an opportunity to provide their views.

The EAO developed a report on its findings from a field assessment of the project site, documentation from Prince Rupert Gas Transmission Ltd. and information from First Nations, Gitanyow Hereditary Chiefs, Gitxsan Wilps and members of the public for the decision-maker’s consideration. Only construction and other project-related activities by the proponent up to Nov. 25, 2024, were considered.

As outlined in his reasons for decision, the chief executive assessment officer determined that the physical work completed is consistent with standard pipeline development, and together with other activities and investments undertaken, the company demonstrated a strong intention to advance the project in the near term.

Substantial start determinations are made on a case-by-case basis, considering all relevant facts. Substantial start determinations are commonly delegated by the minister of environment and parks to the EAO’s chief executive assessment officer.

EAO compliance and enforcement officers will continue to monitor the PRGT project throughout construction and operation to ensure the project meets all requirements in the project’s environmental assessment certificate.

The PRGT project was approved in 2014 to run about 900 kilometres between Hudson’s Hope in northeastern B.C. and Lelu Island near Prince Rupert (the site of a previously proposed, but since cancelled, LNG processing facility). The project as approved includes both land and marine sections of pipeline, along with compressor and metering stations.

The PRGT project was acquired from TC Energy Corporation by Nisga’a Nation and Western LNG in March 2024, to supply natural gas to the proposed Ksi Lisims LNG facility, a project the EAO is currently assessing.

Prince Rupert Gas Transmission Ltd. applied to the EAO in 2024 to change the pipeline route to end on Pearse Island at the proposed Ksi Lisims LNG site. This amendment request is currently being assessed by the EAO.

The EAO is also assessing a separate amendment request received in 2024 to reroute the eastern portion of the pipeline between Chetwynd and Mackenzie, which includes moving the route south to follow part of an existing cleared right of way and shortening it by about 50 kilometres.

The PRGT pipeline project would transport approximately 2 billion cubic feet of natural gas per day, with capacity to expand to about 3.6 billion cubic feet per day.

Share

Get smarter on the 🇨🇦 construction industry in just 5 minutes

Sign up for the free weekly newsletter for news, trends and insights in the Canadian construction industry.

40 Under 40 In Canadian Construction

Nominations for 2025 are now open!

Back for a sixth year, the Top 40 Under 40 in Canadian Construction awards are looking for the next generation of young leaders driving innovation in the industry.

Nominate someone

Topics

PeopleProjectsTechnologySustainabilityRecruitmentEconomy

Newsletter

Get the 5-minute, weekly newsletter about the Canadian construction industry.

© SiteNews 2025. All rights reserved. SiteNews is an independently-operated news website. Views expressed are that of the editor's and are based on publicly available information unless otherwise noted through sponsored content.