Alberta data centre power plant approved by regulator
The news comes as the province is poised to enhance restrictions on data centre development.

Key Takeaways:
- The Alberta Utilities Commission granted conditional approval to Northbridge Power GPC Inc. for a 1,494-megawatt natural gas-fired thermal power plant in Rocky View County, located roughly three kilometres east of Calgary, to fuel a co-located AI data centre.
- The regulatory approval was issued one day before Alberta introduced Bill 42 which would enforce sweeping restrictions on data centre development.
- Construction on the power plant must be finished by Aug. 31, 2029, under strict conditions.
The Whole Story:
Alberta’s utilities regulator has granted conditional approval for a massive natural gas-fired power plant just east of Calgary to fuel a proposed artificial intelligence data centre — a decision issued one day before the provincial government unveiled sweeping new rules aimed at reining in data centre impacts on farmland, water and power bills.
The Alberta Utilities Commission (AUC) issued the approval order on Tuesday to Northbridge Power GPC Inc. — acting as general partner for Indus Power Generation LP — for the Beacon AI Centers – Indus Project Thermal Power Plant.
Located in Rocky View County roughly three kilometres east of Calgary and two kilometres northwest of the hamlet of Indus, the facility is approved to generate up to 1,494 megawatts. Under the project’s application, the plant is designed to supply approximately 1,200 megawatts directly to co-located data halls for AI and high-performance computing.
The regulatory green light came on the eve of the Alberta government introducing Bill 42, the Energy, Environment and Utilities Statutes Amendment Act, 2026, on Wednesday. If passed, the legislation will establish minimum 600-metre setbacks between homes and data centres of 10 megawatts or larger, ban large facilities from irrigated land and prime Class 1 and 2 farmland, and push cooling water consumption close to zero.
The proposed legislation would also force data centre developers to pay for their own power infrastructure costs, while requiring facilities to power down first during grid emergencies.
“Albertans told us what matters most: their communities, farmland and water. We listened,” Technology and Innovation Minister Nate Glubish said. “These proposed rules would make sure AI data centres grow in Alberta on Alberta’s terms, with clear protections for communities and the certainty investors need to build here.”
For the Indus power plant, the AUC attached a suite of strict conditions governing noise, emergency preparedness and eventual site cleanup.
The approved plant will rely on two distinct generating systems: 100 natural gas-fired reciprocating engines capable of producing 4.6 megawatts each, alongside 12 gas turbines paired with four steam turbines in a combined-cycle configuration.
Because of the site’s proximity to nearby residents and livestock, the AUC order requires Northbridge Power to submit a final noise impact assessment at least 90 days before construction begins. That assessment must account for the cumulative sound levels of the power plant and the data centre operating simultaneously, as well as mitigation measures for operational venting and high-noise commissioning steam blows.
The company must also provide advance notice to area residents before high-noise activities, maintain a formal noise complaint response process and complete a comprehensive post-construction sound survey — including an evaluation of low-frequency noise — within one year of the plant and data centre operating concurrently.
On safety, the regulator ordered Northbridge Power to file a project-specific emergency response plan at least 90 days prior to construction, confirming the plan has been reviewed with Rocky View County Fire Services.
To ensure taxpayers are not left on the hook for future cleanup, the approval mandates a progressive reclamation security schedule. The company must post 5% of the estimated third-party decommissioning and reclamation costs by the end of its first year of operation, increasing the security annually until it covers 100% of the costs by Year 20. Independent cost estimates must be updated every five years without deducting potential scrap or salvage value.
Under the commission’s order, construction on the power plant must be completed by Aug. 31, 2029.